The Accelerator Is Now Officially commissioned
10.02.2026

Testing of the accelerator components has now been completed, and last Friday a handover document was signed with the manufacturer’s representative, officially transferring the system to the F2 team. Three beamlines have already been aligned and fully tested, while two (PIXE and the microbeam) still require some fine alignment. In addition, several other system components are currently being tuned. After these tasks are completed, and prior to the start of regular operation, additional monitoring of possible radiation (X-ray, gamma, and neutron) by SVPIS is planned, which is expected to take place next week. Consequently, regular measurements are anticipated in approximately two weeks.